Busbar Trunking System, Minebea, Lincoln
The project was to design, supply and install 900m of Busbar trunking system to the NMB Lincoln factory.
All works were completed out-of-hours to enable the factory to maintain continued production.
Client: NMB - Minebea UK Ltd
Project Duration: 16 Weeks
Completion Date: March 2017
Value: £189,409.00
Our Projects
Lovell- The Spires, Branston
New Offices and Depot, Meadow Lane, North Hykeham
8th January 2021
Domino’s Pizza Wellingborough
20th June 2017
Latest news
Subcontractor of the Month Achievement Award
19th May 2021
Coronavirus
8th January 2021
Testimonial following 5 year Periodic Testing at Bishop Grosseteste University
7th March 2018
Get in touch
Our dedicated management, estimating and technical team are more than happy to help. Our NICEIC registration gives you the support and peace of mind that the products and services we provide are among the best in the industry.
M Gladwin Electrical Contractors Ltd
Unit B4, Paving Way,
Whisby Road,
Lincoln LN6 3QW
Find us on Google Maps
Tel. 01522 716878
Fax. 01522 685976
We are open 8am til 5pm Monday to Friday.